Adelphi Masterfil’s comprehensive testing program ensures complete production security
September 21, 2021
As part of Adelphi’s commitment to quality, production security is guaranteed by our comprehensive 5 stages of testing including:
Stage 1 – Build:
- Key requirements of customer specification are checked against drawings
- Pneumatic components are checked for any leaks
- All nuts and bolts are checked to ensure correctly tightened
Stage 2 – Dry Test:
- Individual components are run on one of our workshop test rigs for 2 days
- Product cylinders are disconnected and the machine is run for 2 days to check for any loose parts
Stage 3 – Wet Test:
- Run with both water and product (if possible), the machine will undergo testing before calibration to check for leaks
- Once calibrated it is run for 10 runs of containers
- Consistency of each head is checked to ensure they are all within our workshop set tolerance
Stage 4 – Pre FAT:
- In house accuracy testing on the customer’s required fills
- Testing is constant while the machine is set to various output speeds and automated functionality setting to ensure capability
Stage 5 – FAT day:
- Machine is tested with customer present or via video to demonstrate ability to meet customer requirements.